Component Replacement (Prop A) 2023
Component Replacement (Prop A) 2023
Project |
Estimated Cost |
Anticipated Start Date |
Anticipated Completion Date |
Project Status |
---|---|---|---|---|
Flooring Replacement |
$5,842,925 |
AUG 2024 |
SEP 2027 |
|
Chiller & Cooling Tower Replacement |
$14,103,221 |
JUN 2024 |
DEC 2027 |
|
HVAC Equipment Replacement |
$407,029 |
MAY 2024 |
AUG 2025 |
|
Building Controls Replacement |
$17,977,728 |
JUN 2024 |
DEC 2027 |
|
Water Softener Replacement |
$500,000 |
APR 2024 |
MAY 2025 |
|
Re-Roof & Building Envelope |
$62,409,601 |
DEC 2023 |
SEP 2027 |
|
Stage Curtain Replacement w/ Flame Retardant Curtains |
$910,000 |
APR 2024 |
SEP 2025 |
|
Chalk Board Removals & Replacement w/ Marker Boards |
$2,250,000 |
APR 2024 |
DEC 2025 |
|