Component Replacement (Prop A) 2023
Component Replacement (Prop A) 2023
Project | Estimated Cost | Anticipated Start Date | Anticipated Completion Date | Project Status |
---|---|---|---|---|
Flooring Replacement | $5,842,925 | AUG 2024 | SEP 2027 | |
Chiller & Cooling Tower Replacement | $14,103,221 | JUN 2024 | DEC 2027 | |
HVAC Equipment Replacement | $407,029 | MAY 2024 | AUG 2025 | |
Building Controls Replacement | $17,977,728 | JUN 2024 | DEC 2027 | |
Water Softener Replacement | $500,000 | APR 2024 | FEB 2025 | |
Re-Roof & Building Envelope | $62,409,601 | DEC 2023 | SEP 2027 | |
Stage Curtain Replacement w/ Flame Retardant Curtains | $910,000 | APR 2024 | SEP 2025 | |
Chalk Board Removals & Replacement w/ Marker Boards | $2,250,000 | APR 2024 | SEP 2025 |