Technology
Technology
Project | Estimated Project Cost | Anticipated Start Date | Anticipated Completion Date | Project Status |
---|---|---|---|---|
Campus Retrofit: 2018-2019 Elementary: Stephens; Sundown; WoodCreek; Davidson; Randolph | $3,467,282 | August 2018 | July 2019 | Completed |
Campus Retrofit: 2019-2020 Elementary: Pattison, Holland, Morton Ranch, Alexander; Kilpatrick, McRoberts Junior High: WoodCreek, Cardiff, West Memorial, Katy, Mayde Creek, Morton Ranch High School: Opportunity Awareness Center Raines, Miller Career & Technology Center, Cinco Ranch | $12,081,511 | August 2019 | July 2020 | Completed |
Campus Retrofit: 2020 Elementary: Franz, Exley, Mayde Creek Junior High: Beckendorff High School: Mayde Creek, Morton Ranch | $7,038,20 | August 2020 | December 2020 Updated to June 2021 | Completed |
Replacement of Network Access Switches Replacement of Network Access Switches General Project Info | $3,621,200 | June 2018 | December 2019 | Completed |
Upgrade of Wireless Access Points & Controllers Upgrade of Wireless Access Points & Controllers General Project Info | $2,204,500 | June 2018 | October 2019 | Completed |
Network Security Infrastructure Network Security Infrastructure General Project Info | $1,280,000 | June 2018 | July 2019 | Completed |
Server Lifecycle & Growth Server Lifecycle & Growth General Project Info | $2,000,000 | January 2018 | December 2020 | Completed |