Skip To Main Content

Toggle Close Container

Mobile Main Nav

Mobile District Home

Mobile Buttons Wrapper

Elementary Schools Toggle Container BTN

Junior High Schools Container BTN

High Schools Toggle Container BTN

Other Programs Toggle Container BTN

Elementary Canvas Menu

Junior High Canvas Menu

High Schools Canvas Menu

Other Schools Canvas Menu

Header Holder

Header Rating Nav - Mobile

Header Top

Toggle Schools Container

Header Rating Nav - Desktop

Translate

Toggle Menu Container

Header Middle

Header Icons Nav

Header Sticky

Schools Canvas Menu - Desktop

Close Canvas Menu

Schools Tabs

horizontal-nav

Breadcrumb

Component Replacements

Component Replacements

Project

​Estimated Project Cost

Anticipated Start Date

Anticipated Completion Date

​Project Status

Mayde Creek Elementary & Mayde Creek Junior High Foundation Repair Work

Mayde Creek Elementary & Mayde Creek Junior High Foundation Repair Work General Project Info

Mayde Creek Elementary & Mayde Creek Junior High Foundation Repair Work Photo Gallery

Mayde Creek Elementary & Mayde Creek Junior High Foundation Repair Work Video

$1,198,274

​June 2019

July 2019

Completed

 

Chiller Replacements

Chiller Replacements General Pr​o​j​​ect ​Info​

​​Chiller Replacements Photo Gallery

Chiller Replacement Video

​$11,223,000 January 2018​ September 2019​
Completed

Boiler Replacements

​​Boiler Replacements General Project Info

Boiler Replacements Photo Gallery

Boiler Replacements Video

$847,000 January 2018​ July 2019
Completed

​​Roof Replacements

​Roof Replacements General Project Info​​

Roof Replacements Photo Gallery

Roof Replac​​ement - Construction​

​$7,983,720 January 2018 July 2020​
Completed

Interior & Exterior Lighting Retrofits

​​Interior & Exterior Lighting Retrofits General Project Info

​​Interior & Exterior Lighting Retrofits Photo Gallery

Interior & Exterior Lighting Retrofit Video​

​$4,785,000 January 2018​ October 2020​
Completed

Athletic Surface Replacements

​Athletic Surface Replacements General Project Info​​

Athletic Turf Replacement - video

Photo Gallery- CRHS​​​

Photo Gallery - KHS

​$5,578,650 January 2018 July 2020
Completed

Natatorium Component Replacements

Natatorium Component Replacements General Project Info​

Natatorium Component Replacements Photo Galle​ry

Natatorium Co​mponent Replacement Video

​$1,019,000 January 2018 September 2020
Completed

Cinco Ranch Junior High & Cinco Ranch High School Kitchen Renovations and Campus Floral Coolers

Cinco Ranch Junior High & Cinco Ranch High School Kitchen Renovations and Campus Floral Coolers General Project Info

Kitchen Renovations Photo Gallery

Video - Kitchen Renovation

​$4,815,102 August 2018​ August 2019
Completed

​Flooring Replacements

Flooring Replacements General Project Info​

​Flooring Replacements Photo Gallery

​Videos

MRHS - Tile Installation​

​OAC - Gym Floor

​$6,489,948 January 2018 July 2020
Completed

Scoreboard & Sound System Replacements

Scoreboard & Sound System Replacements General Project Info

Scoreboard & Sound System Video

Scoreboard & Sound System Replacements Photo Gallery

​$925,000 January 2018​ July 2020​
Completed

Controls Replacement

​Controls Replacement General Project Info

Controls Replacement Photo Gallery

Controls Replacement Video

​$7,119,200 January 2018

August 2021

Updated to February 2022​

Completed

Total $51,983,894