​Component Replacement - 2017 Bond

​Project

​Estimated
Project Cost

Anticipated Start Date

​Anticipated Completion Date

​Project
Status

​​Mayde Creek Elementary & Mayde Creek Junior High Foundation Repair Work

​$1,198,274

​Dec​ember 2017

July 2018


In Progress

​​Chiller Replacements

​$11,223,000

 January 2018​

 July 2019​

In Progress 

​Boiler Replacements

$847,000

January 2018​

July 2018​

In Progress

​​Roof Replacements

​$7,983,720

January 2018

 July 2020​

In Progress 

​​Interior & Exterior Lighting Retrofits

​$4,785,000

 January 2018​

 July 2020​

In Progress  

​Athletic Surface Replacements

​$5,578,650

January 2018

 July 2020​



In Progress     

Natatorium Component Replacements

​$1,019,000

 January 2018​

 July 2019​

In Progress  

Cinco Ranch Junior High & Cinco Ranch High School Kitchen Renovations and Campus Floral Coolers

​$4,815,102

October 2018​

July 2019​


Planning  

​Flooring Replacements

​$6,489,948

January 2018

 July 2020​

In Progress 

​Scoreboard & Sound System Replacements

​$925,000

 January 2018​

 July 2020​

In Progress 

​Controls Replacement

​$7,119,200

​ January 2018

​ July 2020

In Progress

Total                                               $51,983,894

"" 


TEA Met Standard - District & Campuses

6301 S. Stadium Lane - Katy TX 77494 | 281.396.6000 | Login | Accessibility

It is the policy of Katy ISD not to discriminate on the basis of sex, disability, race, religion, color, gender, age, or national origin
in its educational programs and/or activities, including career and technology programs, nor in its employment practices
and to provide equal access to the Boy Scouts and other designated youth groups.

Katy ISD is not responsible for the content on external websites or servers.