Mayde Creek High School Athletic Modifications Construction Manager @ Risk: Sterling Structures,
L.P. Description: Specific school community concerns were identified in December 2004 related to the condition of certain athletic field components at Mayde Creek High School. Since that time, Facilities personnel have addressed immediate maintenance needs and have investigated other functional requirements. It was the recommendation of administration that various components of work be undertaken to improve specific athletic field facilities. The outcome of a programming exercise, and review of the MCHS athletic facilities, was a master plan of the athletic complex which included the following components:
The project will be undertaken in such a way as not to negatively impact field activities and will be substantially complete by July 2005. |