Mayde Creek HS Roof/Building Envelope
|
Project Summary
- Budget: $3,202,825 (includes both Fielder ES & Mayde Creek HS)
- Approved Construction Cost: $3,202,825 (includes both Fielder ES & Mayde Creek HS)
- Architect/Engineer: PBK Roofing
- Contractor:
Con-Tex Services, LP - Made Creek HS Remedy Roofing - Fielder ES
- Project Completion:
Fielder ES - August 2011 Mayde Creek HS - December 2011
Description: Replacement of roof system.
Background/Justification: This is a built up roof with gravel surface. The roof areas to be replaced at Mayde Creek High are 27 years old. The roof is failing. Large repairs have been made in the field of the roof. The vent curbs are deteriorated and expansion joints and roof drains leak. Leaks have been so numerous and over such an extended period of time that interior damage has resulted.
Phase 1 2010: Remove and replace the roof areas B1-B18, remove and replace the translucent wall panels around the gyms at area C4-C5 and the translucent skylight panels at area C3. This included exterior waterproofing, replacement of through wall flashings and A/E fees. A roof plan with the referenced area designations has been attached.
Future Bond - Phase 2- recommended year: Remove and replace the roof areas C1-C15 and D1. This included exterior waterproofing, replacement of through wall flashings and A/E fees. The above information is not only supported by District staff but an outside roofing consultant.
|
|
|
|
|
|
|
|
|
|
|
|
|
|