Fielder ES Roof/Building Envelope
|
Project Summary
- Budget: $3,202,825 (includes both Fielder ES & Mayde Creek HS)
- Approved Construction Cost: $3,202,825 (includes both Fielder ES & Mayde Creek HS)
- Architect/Engineer: PBK Roofing
- Contractor:
Con-Tex Services, LP - Mayde Creek HS Remedy Roofing - Fielder ES
- Project Completion:
Fielder ES - August 2011 Mayde Creek HS - December 2011
Description: Replacement of roof system.
Background/Justification: The built up roof system with gravel surface was installed 1993. The material warranty ended 2003. Five entry areas are pre-finished standing seam metal. Numerous leaks have been addressed around the metal entries, expansion joints, thru-wall and penetrations. The roof edge and gutters are in poor condition. Several areas on the field of the roof are exposed felt only; possibly due to directional weather conditions. Interior repairs have been made multiple times in multiple locations.
The above information is not only supported by District staff but an outside roofing consultant.
|
|
|
|
|
|
|
|
|
|
|
|
|
|